Farm Bridge Latest


Farm Bridge Delay?

I visited the site today (24 Aug) to find mud everywhere. The recent heavy rains have taken their toll. Mid- September was the original completion date.
I spoke to the Site Manager about completion dates and, reading between the lines expect a delay of at least a week. It could even be early October before everything is tidied up.

Friday, 6 August 2010

Holdingham Houses and Flats near A17


I managed to get to speak to the Site Manager the other day: and he informed me that the first occupents should be in by late October. Initially it should have been September but that date is likely to be missed due to electricity supplies to tje site.


The first houses to be taken by new residents will be those near the A17 - the flats nearer the B1518 (Lincoln Road and mini-roundabout) will not be inhabited for the time being as there will be vehicle movements there.


Hope this makes sense!

Tuesday, 3 August 2010

Starting work on the Farm Bridge!


I was stopped today from going onto the Farm Bridge. Work has just started! There is a barrier across the bridge itself - I assume work will be complete by September 14th.